18
Plant Design and Cost
Russell T. Roane
1.0 INTRODUCTION TO THE CAPITAL PROJECT LIFE
CYCLE
Capital cost projects begin when a need is defined that cannot be
satisfied in existing facilities. Thus begins the life cycle of a capital project
(Fig. 1). Once started, the project will progress through all of the following
phases or be canceled. It all starts with the recognition of a need that will
require capital plant. In the conceptual phase of the project, multiple
approaches will be evaluated and one or more plans will be evaluated for
meeting these needs. The conceptual plan, if a process plant, will be defined
in plant configuration drawings and process flow diagrams; if an architec-
tural project, by plant configuration and programming documentation. If it
is a process plant, then a process flow scheme must be generated and a
configuration for the facility conceived including any support requirements
that must be included for the operation to function. Ifan architectural project,
then all the spaces must be defined and the programming completed to a stage
that assures that all required building functions are provided. Most times this
phase is concluded with an order of magnitude estimate that is used to assess
the economic viability of the project.
759
760 Fermentation and Biochemical Engineering Handbook
CAPITAL PROJECT
LIFE CYCLE
CONCEPTUAL DESIGN
PRELIMINARY DESIGN
DETAILED DESIGN
CONSTRUCTION
FULL OPERATION
START-UP
Figure 1. The life cycle of a capital project.
The second phase is normally calledpreliminary engineering and its
objective is normally two fold: sufficient engineering to achieve overall
definition of scope for the project and establish a firm budget for completion
of the project. The estimate prepared at this point is normally called the
authorization estimate. With this information, the decision is made on
whether the project is to be completed. To get to this point usually takes
between 15 and 30% ofthe total design cost. Some will call this the definition
phase of the project.
Next is the main design phase of the project, normally called detailed
engineering. During this phase of the project, the design of the facility is
completed and the procurement for the project begins. The equipment is
specified and purchased. All required design documentation is prepared and
assembled into bid packages preparatory to construction. Somewhere during
detailed engineering, the authorization estimate may be updated to become
what some call the control estimate or, in an effort to more tightly control
cost, this may bemanaged by continual tracking ofthe authorization estimate.
The project is then taken to thefield. This is the construction phase of
the project. This phase of the project can be managed with several types of
organizations. In construction management form, the engineer, architect, or
owner, puts together a construction management team. The work to be
executed is then specified in subcontracts. Each subcontract contains the
work centered around one craft or construction trade. The construction
management team is then responsible for seeing that the work is completed
on time, as specified (of acceptable quality), and that field costs are controlled
Plant Design and Cost 761
to budget. In direct hire form, the construction management team is
expanded to allow direct supervision ofthe craft workmen on the project and
the responsibility for performance ofthe subcontracts is not delegated. As the
name implies, the craft workmen are directly hired. In the third form, general
contracting, amulticrafted or key contractor is hired and he then becomes the
responsible party for execution of the work. He will perform the project
utilizing his own employees and subcontracting the craft work not common
to his work force. In this form, quality oversight must be accounted for and
performed. Construction’s normal objective is what is termed mechanical
completion. Mechanical completion is normally defined as a plant that is
fully assembled and has been checked for operability, but has not been
performance tested. An agreed level of clean out is part of mechanical
completion. The project is ready for start-up, not operation.
Start-up is a transition phase between mechanical completion and
dedication to full operation. It includes performance testing, final clean out,
trial production phase, and the first full scale operations. Water batching is
a common means of achieving both clean out and testing. Where water
batching is not appropriate, solvent testing may be used, or selected as a
second step, to achieve dry out and testing. The objective of either is to test
the plant and prepare it for trial operation. Trial operation will be planned
to risk a minimum amount of materials to performance-test the operation. It
can take many forms, Le., reduced operation through low flows, smaller
batches, or utilization of substitute materials. The start-up phase is best
shared between the designers, the constructors, and the plant operators. The
designers contribute how the plant was designed to operate, the constructors
do the required mechanical work, removing and replacing items of temporary
installation, assisting with commissioning of specialty equipment, mechani-
cal adjustments, and other corrections that appear as the start-up progresses,
and the operating people learn how to operate their plant. Start-ups are best
managed by the operations people with assistance by the other support
groups. It is important to consider the people as well as the equipment in
planning the start-up.
Overstaffing can lead to methods ofoperation that are expeditious, but
not sustainable for the plant to be profitable. The plant staff is best supported
by staff that plans to leave the project. When the plant proves itself capable
of full operation by unaugmented staff, it can be declared out of start-up and
dedicated to plant operations.
These are the phases that a capital project passes through from
inception to dedication. Overlapping of the phases and compression of
schedule is commonly achieved through an approach calledfast trachng. It
762 Fermentation and Biochemical Engineering Handbook
comes to the fore any time where the benefits of early completion outweigh
the added costs. Some will argue that there is no added cost since fixed costs
are reduced to offset the limited inefficiency of redo required. What can be
agreed upon is that there is an optimum balance for each project, and time
spent finding it will help to assure that the project will be a success.
2.0 CONCEPTUAL PHASE
The conceptualphase of a project starts before there is a project. This
phase of the project is where a plan for satisfying a need will be conceived
(Fig. 2). Definition of the need will start the process. A method of satisfying
the need will be the result. The need may be for increased capacity, new
product, elimination of bottlenecks in existing facilities, modernization,
meeting new regulations, energy efficiency, and waste minimization, to name
a few.
CONCEPTUAL PHASE
A NEED MUST BE FILLED
THE FIRST SOLUTION
Figure 2. The conceptual phase.
One good approach at this time is to prepare multiple solutions and
hope to find an optimum solution. Realize that this is the phase where the
optimum solution can be found most economically, beyond this phase the
solution chosen can be optimized, but to change the chosen solution will
require return and restart at this phase with a large portion ofthe work of later
phases discarded.
The most important element at this phase of the project is that the
project team shall have a varied experience base, Le., creating plans to satisfy
needs is easily facilitated. Success comes with a team strong in three ways.
(i) experience in the industry, (ii) experience in the various skills required for
the project, and (iii) experience in this creative period of a project.
Plant Design and Cost 763
This phase of a project is best guided by the statement of the need.
Example: “The sales projections for our product exceed our production
capacity starting the middle of next year”.
Start with the statement and collect ideas for solutions. Next, evaluate
the solutions and select the ones with the most favorable features for further
evaluation. As part of the evaluation procedure, determine the “must have”
features and the “would like” to have features. The final selections should
have all the musts and as many of the high ranked wants as can be
accommodated. Some of the ideas will be found unsuitable as their
development begins.
Take the three or five best ideas and develop them with the objective of
finding out their space requirements and their equipment requirements.
Develop them sufficiently to produce a first order cost comparison. In this
phase of the project, the objective is to do sufficient development so that two
things are established: (i) which solution you have uncovered best satisfies the
need at a justifiable cost, and (ii) what is the first order estimate ofthat cost.
Warning: The most overlooked items are not core to the process, but are
required as support for the project, i.e., facilities to produce utilities at the
capacity required; sufficient laboratory, warehouse, waste disposal, or in-
process storage.
Each solution must be given an overall evaluation for hazards that
impact safety and potential monetary loss. This need not be an itemized,
comprehensive review but it should encompass hazards to the employees and
the environment, loss due to fire, or unplanned equipment failure, and most
important, release of hazardous raw material, intermediate, or product.
This phase of the project is complete when a cost-effective means of
fulfilling the deked need has been identified and estimated. Cost estimates
at this stage in the project are not very accurate; plus or minus 50% is the
norm. It is the basis for the decision whether to go ahead with additional effort
to firm up the project’s budget. Many projects are underfimded and not viewed
as a success if the estimate produced at this stage is used to fund the project.
3.0 PRELIMINARY DESIGN PHASE
The preliminary design phase is where sufficient work is done to
estimate the cost of the project to an accuracy that is consistent with the
sponsoring organization’s requirements for funding of a project. Estimating
accuracy will be related to the percentage of total design cost spent.
Estimating accuracy is usually in the range of 2 15% to +30%. A frequently
764 Fermentation and Biochemical Engineering Handbook
experienced case is that of a +25% estimate with +30% of design cost
expended.
The preliminary design phase is also where sufficient design work is
done to assure operability of the project without additional scope. The first
step is to evaluate what work must be done to assure that the required scope
is comprehensive for the project: what work must be done, to what detail, to
achieve the required accuracy of the estimate (Fig. 3). If a conceptual
estimate has been made, a quick study of it shows which are its largest
accounts and then focus can be on the improvement of their accuracy. A
second review that is painfully forgotten is the evaluation of the project for
overall completeness of the scope. Questions to ask at this point are:
Are emissions suitable for permitting with the current design?
Are treatment solids also disposable?
Are there previous commitments that become part of this
Are utilities sufficient and available where required?
Are utility systems suitable for permitting at the increased
Are the following sufficient: Offices? Laboratories?
Solid? Liquid? Gas?
project?
rates?
Warehouse? Roadway? Site drainage? Security? Phone
system? Fire protection?
Are current operations impacted (Le., grandfathering re-
moved)? Buildings? Processes? Other planed services?
Is building construction compatible with the need? Fin-
ishes? Seismic? Height? Relief requirements?
Have all plant hmiture and vehicles been included?
PRELIMINARY DESIGN
IS THE SOLUTION FEASIBLE?
IS THE SOLUTION COMPLETE?
IS THE ESTIMATE SUITABLE?
Figure 3. The preliminary design phase.
Plant Design and Cost 765
Here is but a partial list ofthe questions to be asked so that unestimated
scope does not enlarge the project beyond its estimated accuracy and interfere
with its profitability. At some point in preliminary design, a project logic
meeting is in order where the sole focus is uncovering potential flaws in the
project’s logic. A blend of those most knowledgeable about the project and
seasoned evaluators less immediately involved with the project can best
perform this effort.
If the project has sizable architectural considerations, it is important
they be properly estimated. Those dollars per square foot numbers that are
so useful early in the project need to be firmed up. For the biotech and dosage
pharmaceutical projects of today, it is as important that the building costs be
as accurate as the equipment costs. Sometimes an account-by-account
evaluation for estimating accuracy is in order to see if sufficient work has
been done to assure the validity of the overall estimates accuracy.
4.0 DETAIL DESIGN PHASE
The detail design phase of a project is where most of the cost of a
project is committed. During this phase of the project, the design work is
completed and most of the equipment purchased. The focus for this phase of
a project is to turn all of the plans developed to date into a purchasable and
buildable set of documentation (Fig. 4). To expedite the schedule, the
construction contract may be let as this phase is being completed. Changes
made during this phase of a project tend to be very costly as they result in the
discarding of work and materials for which recovery will be minimal. For this
reason, it is important in controlling costs to make the transition into this
phase of the project with the scope approved and complete. If items are yet
to be decided, it is important that they be clearly defined as undecided items
so that when the decisions are made work need not be repeated.
DETAIL DESIGN
IS THE DESIGN COMPLETE?
CAN THE DESIGN BE CONSTRUCTED?
Figure 4. The detail design phase.
766 Fermentation and Biochemical Engineering Handbook
During this phase of the design work the scope established in the
preliminary phase of the project is divided into work packages for award as
subcontracts or, ifthe construction is done on a direct hire basis, they become
the work packages for the various crafts.
Some discussion is in order at this point to differentiate between what
are called the architectural and engineering approaches to detailed design
and construction. Most projects in the food, pharmaceutical, and biotech
industries require a blend of these two techniques of design. In the
architectural approach, detailed design is completed by mechanical design
subcontract or inclusion in construction subcontracts. With the engineering
approach, the detailed design is completed as part of one engineering effort.
The architectural approach passes on the engineering by written functional
specifications describing how the installation is to function, not how that
function is to be achieved. The engineering approach details how each
function is to be achieved. Each approach has its proponents and its
detractors. By looking at only the cost of the primary design work, the
architectural approach will appear less expensive. It is the writer’s opinion
that the architectural approach is very good for designs where utilization of
repeated, well-understood elements is a major component of the work, (i.e.,
the building part ofthe project). The engineering approach is better where a
process is being installed (the process design). The disadvantage in utilizing
the engineering approach to the building is that, many times, it does not allow
completion to occur with mixes and matches of materials that lower final
installed cost. A secondary disadvantage is that the tendency in engineering
approach is for unique design elements that restrict competitive bidding to
reduce cost. The disadvantage to the architectural approach is that the design
work can more easily slip into the hands ofthose who do not fully understand
the functionality of what they are being asked to achieve. Also, design
documentation required for regulatory review and compliance becomes
available later. Because the engineering approach allows an estimate in better
detail at an earlier point in the project, it allows better budget and schedule
control. In summary, if this is an all-process building, use the engineering
approach ; if just offices and laboratories, use the architectural approach;
and, if a blend (as are most projects in this industry), use a blended approach
to cost effectively achieve your objectives.
Remember that, when organizing for the detail design phase of a
project, the design will be a complex and detailed undertaking. Be sure that
sufficient documentation takes place to ensure that those who turn it into a
completed operating facility have sufficient information to properly under-
stand what they are to achieve.
Plant Design and Cost 767
5.0 CONSTRUCTION PHASE
The construction phase (Fig. 5 .) of a project can be accomplished in
three main ways-construction management, general contractor, and con-
struction by direct hire.
CONSTRUCTION
WHERE DESIGN BECOMES REALITY
Figure 5. The construction phase.
The construction management approach utilizes a construction man-
ager or a management team to manage and control the project, depending on
project size. The project management can be from a group on staff with the
owner, individuals hired for the duration of the project, or a contracted effort
from a firm that specializes in these abilities. This project management team
is responsible for the budget, schedule, and quality of installation. They have
sufficient people on their team to assure that the work is proceeding on time,
within budget, and is being constructed according to specifications. The
physical work is accomplished through subcontracts awarded to individual
companies to complete separated scopes of work that are within there
acknowledged skills. These skills most often parallel those of the design
discipline engineers: electrical, mechanical, civil, structural, etc.
The general contractor approach gives the responsibility for construc-
tion management to a construction contractor. Most often this contractor will
be the one who will also hold the largest subcontract on the project. The major
advantage of the arrangement is lower cost. It does not, however, come
without price. The contractor selected may not have the qualified people to
control the parts of the job in which he has no expertise, he may add parts of
the project to his work scope that he is not qualified for, and the work he self-
performs will not have the advantage of checks and balances on its quality.
The direct hire approach is used by those calling themselves construc-
tors to gain the advantages of construction management in a way that
competes with the cost of the general contractor approach. In this approach,
768 Fermentation and Biochemical Engineering Handbook
the construction management team is expanded to include craft supervisors
and the work force is assembled by moving in a cadre of permanent workers
with the constructor and expanding that cadre with local hires from the craft
work pools in the area. This approach allows the project to be done by a top
flight construction management team, controlling cost and schedule, without
the costly layering ofmanagement that occur in the construction management
approach. This approach can gain the best of both worlds ifthe owner assures
himself that the constructor has a strong quality management program that
allows no compromises on quality in the construction of the facility.
If you reread the above, keeping in mind what was said about the
architectural and engineering approaches in the section on detail design, you
will realize that the negatives of the general contractor approach are
minimized if the project lends itself to the architectural approach, and are
maximized on a project that needs the engineering approach.
An agreed-upon condition on the completion date is an important
project decision that should be made prior to award of construction contracts
and should be made a written part of them. In the past, this was called
mechanical completion, which was generally meant that all equipment was
tested and ran in a mechanically approved manner and proper tests had been
conducted to confirm tightness and pressure rating of system. Only
necessary material for testing the system would be introduced. Today the
requirements for cleanliness and proofing of tests as part of validation
require that the definition of condition for turnover to start-up must be
developed in much more detail. The questions to be asked when developing
the completion plan are:
What part of validation Installation Qualification (IQ’s)
will be completed as part of the construction effort?
What will be the condition ofthe document control files on
completion?
Is water batching or some related form of process simu-
lation without real materials to be included?
What part of validation Operational Qualification (OQ’s)
will be completed as part of the construction effort?
What will be the condition ofthe spare parts that may have
been ordered as part of the project purchases?
What help and checking will the owner supply or exercise
as part of the construction effort?
Plant Design and Cost 769
7 What systems and in what sequence will the plant be
completed and turned over to the owner?
8 What continuing effort are the construction forces to
supply to the start-up effort?
9 Is vendor assistance to be coordinated by the construction
personnel or by the owner’s personnel?
10 Does the owner want access to parts of the facility prior
to completion that will interfere with completion?
These are but a few of the issues to be addressed if the completion of
construction and the start of operations is to be accomplished on a smooth and
efficient schedule.
6.0 START-UP PHASE
Start-up is the transition from completion of construction to full
operation and it impacts both construction and operations (Fig. 6). Many
times, projects have construction scheduled to be completed simultaneously
in all areas. This is neither accurate or the real world. Both construction and
start-up personnel must think in terms of a phased completion because
construction will not have sufficient people to complete every thing at once
and start-up will not have sufficient people, or fimctionality, to start-up the
facility all at once. The sequence of completion needs to be agreed upon early
in the construction effort so that construction focuses on completion in the
agreed sequence and start-up gains availability to start in a logical sequence.
If the last item on the construction schedule is to set the main electrical
transformer andconnect the plant power, no transition to start-up is possible.
There are many more subtle constraints in a construction schedule that can
be prevented with proper planning.
START-UP
MAKING IT WORK
1 DOES IT FUNCTION AS DESIGNED?
Figure 6. The start-up phase.
770 Fermentation and Biochemical Engineering Handbook
The stages of start-up are water batching, followed by low-risk
production, and then, finally, into full production. The last construction
activity is usually mechanical checkout. Pressure testing, rotational testing,
and other testing can be accomplished without the total system being
operational. Water-batching for most plants is simply to make the equipment
operate using water, or another suitable medium, to simulate the operation.
The water batching may be coordinated with and combined with the
completion of clean-out ofthe system. The next phase will vary with the type
of operation that is being started. It can be part-sized batches, running
without the expensive ingredients, or just batching, with only solvents and
water present. Again, planning well in advance will take most of the stress
out of this phase of a project and keep it on schedule.
One of the items to be covered in start-up is manpower planning: what
skills will be required, who will supply them, and what are the quantities?
Operator manning levels tend to justie themselves, so it is not agood practice
to just add more operators for start-up, but rather, to supplement with people
who will not stay with the project once it accomplishes fill operation.
7.0 THE FAST TRACK CONCEPT
Fast-tracking is a much used, but not universally defined approach to
expediting the completion date of a project (Fig. 7). Fast-tracking, in its
simplest definition, is starting construction before the design effort is
complete, in an effort to shorten schedule.
FAST TRACK
AN OPTIMUM SEQUENCE SCHEDULE
DON’T FORGET VALIDATION
DON’T FORGET START-UP?
Figure 7. Fast-tracking.
Plant Design and Cost 771
It has value, if planned properly, as a method for improving schedule
and reducing capital cost. A thorough planning effort is necessary if the
advantages are to be gained without increasing the overall cost. Certain of
the costs of a capital project are time rather than effort related and these costs
are saved when the schedule is shortened. Examples are interest on moneys
expended, supervision at all levels, field rental expenses. These savings do
not come without some loss of efficiency in all of the activities that are the
result of proceeding with incomplete information which results in work being
repeated. Each project has its optimum schedule, balancing cost with
schedule.
The ultimate fast track approach plans detailed design, construction,
start-up, and validation, as one coordinated effort. The key components of
the plan are the decisions made on the sequences of completion. This
sequence determines the priorities of construction and start-uphalidation.
Construction then determines the sequence for detailed design and a critical
path determines the overall schedule. The critical path can then be optimized,
using negotiations among the various groups to shorten key critical path item
schedules. The planning for this effort is not insignificant, but ifplanned and
done in this manner, it does pay dividends in reduced cost and shorter
schedules.
8.0 THE IMPACT OF VALIDATION
Today’s biotech, pharmaceutical, or fermentation project, requires
that a validafion effort be completed prior to producing saleable product (Fig.
8). Looking at the validation activity as an afterthought is not being cost or
schedule effective. An effective way to think about validation is the
following: is the project suitable for validation? A validation study during
conceptual engineering will answer that question. The magnitude and the
specific steps for validating the facility are addressed by a preliminary master
plan produced during preliminary engineering.
The master plan is finalized during detail engineering. The protocols
prepared (IQ’s, OQ’s and PQ’s) and the validation files started during
construction. The IQ’s (Installation Qualifications) are performable as
construction is completing and can be completed by the constructor under
supervision. The OQ’s (Operational Qualifications) can be performed
during the earlier parts of start-up as verification of mechanical completion.
The PQ’s (Process Qualifications) are performed as start-up completes and
continue through the operating life of the plant. For maximum schedule
772 Fermentation and Biochemical Engineering Handbook
efficiency, the validation schedule should be part ofthe overall project and not
be considered as a separate effort.
VALIDATION
PLAN IT IN
REVIEW BEFORE PRELIMINARY
MASTER PLAN BEFORE DETAIL
PROTOCOLS WITH CONSTRUCTION
IQ’S FINISH CONSTRUCTION
OQ’S FINISH START-UP
PQ’s INTO FULL OPERATION
Figure 8. Validation
9.0 INTRODUCTION TO THE COSTING OF A CAPITAL
PROJECT
As a project progresses, there are many demands put on the costing
effort that proceeds with a project (Fig. 9). The first question is usually, is
this a viable project? The quick, low accuracy estimate possible at the end
of conceptual engineering is called an order of magnitude estimate and
provides, with other business information, the answer of whether the project
is likely to be profitable and should be continued, researched further to reduce
cost, or cancelled as unprofitable. Based on the viability of the order-of-
magnitude estimate, the work to proceed to the authorization estimate is
committed. The authorization estimate is next and the work is dependent on
the individual company’s requirements for authorization ofthe full budget for
the project. The authorization estimate’s purpose is to secure funding for a
project. A control estimate can be prepared near the end of engineering to
achieve higher accuracy when almost all elements of the project have been
quantified and the major ones bid.
Plant Design and Cost 773
COSTING A CAPITAL PROJECT
WILL THE PROJECT BE PROFITABLE?
CORPORATE FUNDING LEVEL?
BRING IT IN ON THE ESTIMATE
Figure 9. Costing a capital project.
If, as with most projects, your project is not overly funded or highly
profitable, then the approach may be to trend the cost throughout the
preliminary and detailed engineering. The reason for trending is to provide
up-to-date information for any cost impact decision as the project progresses.
Whether the formal step approach, or the trending approach with snap-
shots is used, it is essential that a control estimate be created to be used during
construction to control the cost of the constructed project. The result of
shortchanging the estimating and cost control effort are a noncurrent cost
reality and unhappy surprises as to final cost and schedule.
One of the techniques of estimating is to add to the allowance for
undefined sections of the project and then state higher levels of accuracy for
the estimate. Example: add a 20% allowance to a +30% estimate and call
it a 10% estimate. If your concern is not exceeding the estimate, it is possible
to use this technique, but if you add 20% to a plus or minus 30% estimate
and call it a 10% estimate, you really get a plus lo%, minus 50% estimate at
the end, and you are much less likely to come in at the original estimate, for
the reasons mentioned in dynamics of an estimate below.
10.0 ORDER OF MAGNITUDE ESTIMATE
An order-ofmagnitude estimate is made using generalized assump-
tions about the project to estimate its costs. The purpose of an order-of-
magnitude estimate is to decide whether the cost of preliminary engineering
is justified and, with business plan information, whether the project is
profitable enough to continue (Fig. 10). Sometimes this combined effort is
called a feasibility study.
774 Fermentation and Biochemical Engineering Handbook
ORDER-OF-MAGNITUDE ESTIMATE
MINIMUM DOLLARS TO FIRST DETERMINATION
IS IT PROFITABLE TO CONTINUE THIS PROJECT?
Figure 10. Order-of-magnitude estimation.
The method used for the estimate should be developed by a skilled
estimator and approved prior to preparation by those who will be responsible
and present its conclusion. Normally these estimates are approached in two
areas, process and architectural. The process and utility support installations
will be estimated from preliminary pricing of equipment lists. Factors will
then be applied for installation, piping, electrical, instrumentatiodautoma-
tion, hidden scope/contingency, escalation, growth in equipment cost, and
other minor equipment-related costs, such as paint and insulation. The
factors only have significance to those who generated them as they are based
only on related experience and a unique assignment of costs in the base data
accumulation. The overall ratios are not even worth presenting because the
vendor that previously supplied only equipment now packages many features
on that equipment. Included may be sophisticated control packages with both
electrical and instrumentation control features, connected auxiliary equip-
ment, and interconnecting piping.
The architectural portion of the estimate will include both the building
and site costs. The building costs will be based on square feet under roof and
then built up by adding costs per square foot for the improvements as they are
added to the base price. Be carekl at this stage ofthe project and avoid using
a single all-in gross square foot cost for the building. When dealing in the
finished pharmaceuticalhiotech arena by this method, you may be an order
of magnitude wrong in cost, 200 dollars per square foot may turnout easily
to be 2000 dollars per square foot. Be sure to include in this section of the
estimate the site relatedcosts, i.e., those costs that relate to the site rather than
the building. Site costs are based on units of measure similar to those used
forthe building estimate: cubic yards offill, square yards to be cleared, square
yards to be paved, trees and shrubs to be planted by estimated count, and
Plant Design and Cost 775
square yards of grass to be planted. Don’t overlook costs for disposal of
materials to be removed from the site.
Another issue not to be overlooked is site support costs. Do I need to
pay for extension of the rail line, upgrade construction of the local street,
extend sewer or water lines, modi@ electrical source connected to, are but a
few to be considered. The only effective method of covering this adequately
is to study the plant operations and list all the items it will consume or
discharge and mentally walk them back to an adequate connection point.
Beware of utilities that must be generated, the cost of supplies to, and the
discharges from, the generating operation must be included in the estimate.
Only when an in-depth effort is made to uncover hidden scope can it be
uncovered in time to be included in the estimate.
Whatever confidence you have in the estimate, it should not be higher
than the confidence you have in those preparing it for you. The effort put into
exposure of the total scope is equally as important as the estimate itself. No
estimate can accurately reflect an item that was not included in the scope of
the project. An item included, but estimatedpoorly, is better provided for than
an unseen item you think you have provided for by an oversize contingency.
11.0 APPROVAL GRADE ESTIMATE
The approval-grade estimate is normally produced after spending one
quarter to one third of the engineeringlarchitectural design dollars. It’s focus
is twofold with the first being verification of the completeness of the project
scope (Is all we will do in the estimate?). The second focus item is improved
accuracy and detail to better function as the cost control document for the
balance of the project (Fig. 11).
APPROVAL-GRADE ESTIMATE
ASKING FOR THE MONEY
HOW MUCH?
SUCCESS = FINISHING IN THE MONEY
Figure 11. Approval-grade estimate.
776 Fermentation and Biochemical Engineering Handbook
Additional engineering is used to remove factored values from the
estimate by developing sufficient detail to allow the factored values to be
replaced with estimated quantities and unit prices. Equipment purchases will
be updated to reflect the input of quotations received for the equipment. The
building details will be improved as well. The area sizes and layout will be
firmed up. The building estimate will be improved in the same manner, since
it will now be based on takeoff quantities. The building room sizes will be
given a first level confirmation.
The approval estimate is the most important to the reputations of the
managing engineers for the project. A successful project is completed on
time, in budget, and gains a reputation for smooth and efficient operation
shortly after dedication. This is not likely to happen by accident. The
decisions on what is necessary for the smooth and efficient operation are made
during preliminary engineering and funded by approval of this estimate.
If your company attitude, or the project’s justification, require a high
level of assurance that the budget will not be exceeded, then the detail
developed in preliminary engineering will require expenditure of more of your
design dollars in the preliminary engineering stage of the project, but if
properly managed, will not increase the overall design cost.
12.0 CONTROL ESTIMATE
The control estimate is a final confirmation of the cost of the project
(Fig. 12). It is adetailedpricingoftheproject fromtakeoffsofquantities and,
in most cases, will reflect local bids for materials and construction labor. By
the time this estimate is made, the project cost has been decided and this is
done to form a control basis for the project as it proceeds through construc-
tion.
Two forces have combined to make this estimate obsolete as a separate
estimate. One is the modern business need for more precise and up-to-date
reporting of the capital cost of a project. The second is the change to lump-
sum contracts for most of the construction performed on a project in the
biotech/ pharmaceutical arena.
The control estimate has been replaced by a procedure called trending,
or estimate tracking, which is continuous cost estimate tracking leading
directly into cost control as the project’s appropriation is spent. It is a much
more time-responsive way of controlling costs on the project and a snapshot
of the trended estimate can be published as the control estimate at any
appropriate time. It is helpful in today’s world, where immediate
Plant Design and Cost 777
explanations are the norm, to track the job cost from order-of-magnitude to
job completion. Under the complete scenario of tracking, the always
explainable improvement in estimate accuracy can be separated from those
expansions of project scope, and upgrades in design can be separated from
changes in unit costs.
II CONTROL ESTIMATE I
THE FINAL BUDGET
LAST CHECK ON APPROPRIATION
Figure 12. The control estimate
13.0 DYNAMICS OF AN ESTIMATE
Estimates impact a job in more than the cost area. It is these indirect
influences that luckily help to make the estimates the self-fulfilling prophesies
they are meant to be.
Estimates that have caused a project to be redefined and reestimated
tend to return to the original estimate unless the effort at cost tracking (Fig.
13) is intense and finger-pointing.
ESTIMATES DYNAMICS 1
CONTROL THE PROJECT, CONTROL THE BUDGET
PERFORMANCE = BUDGET
PROJECT ON TRACK
Figure 13. The dynamics of an estimate.
778 Fermentation and Biochemicul Engineering Handbook
The simple rules of contracting, no matter what the item, are the
following.
- Everyone will include an estimate for the work, a contin-
gency for the unseen development, and a profit for doing the
item.
- Negotiations for change are easy when the put and take is
from contingency, more difficult when you are asking
sacrifice of profit, and impossible, or almost that, when you
ask the supplier to take a loss.
- Successful projects determine a fair price, including all three
factors, and keep the performance of the work in phase one,
where contingency is all that is being expended.
- When below budget, other concerns on the project are likely
to be given close scrutiny. When the project is running over
budget, then the cost of all items will be scrutinized